Your project is behind schedule due to conflict between team members .Haring resolved the conflict, to get the project back on schedule,you should consider (  ).
A、crashing the Schedule
B、performing resource leveling
C、conducting reverse resource allocation Scheduling
D、utilizing the critical chair resources
 查看答案
                                        查看答案