Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and (  )
	A、fast tracking    
	B、what-if scenario analysis
	C、resource leveling   
	D、critical chain method