A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( )
	A. change the scope baseline
	B. call a meeting of the configuration control board
	C. assign change tasks to project members
	D. postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline