On some projects,especially ones of smaller scope,activity sequencing, activity resource estimating, activity duration estimating, and () are so linked that they are viewed as a single process that can be performed by a person over a relatively short period of time. 
A、time estimating 
B、cost estimating 
C、project planning 
D、schedule development
							