The project has an earned value (EV) of US$1,530, and a planned value (PV) of US$1,630. A team member suggests
	removing a   deliverable to benefit the schedule and positive impact the critical path. After documenting the details, the project manager proceeds?
	A. Submit a change request
	B. Change the project management plan
	C. Recalculate the PV
	D. Perform a reserve analysis