After the project team identified several risks, the project manager wants to analyze these risks on the possible impacts of project results. Which of the following tools should be used ?
	A、Qualitative Risk Analysis
	B、Ishikawa diagram
	C、Decision Tree Analysis
	D、Monte Carlo simulation