The project manager reports a to-complete performance index of 1.15. The budget at completion is US$1,575,000.The earned value is US$ 1 million. The planned value is US$985,000. What is the actual cost ?
	A、US$985,000
	B、US$1,061,957
	C、US$1,075,000
	D、US$1,132,750