After reviewing the project schedule, the project manager realizes that a unique resource on a specific activity on the critical path will not be released on time, but will be available at a later date. What should the project manager do next ?
	A、Work with the critical path method
	B、Ask management for resources
	C、Define activity resource requirements
	D、Apply the critical chain method