In conducting risk analysis for a large project. the project team creates a project model for simulation. The computations are iterative alive with input values such as cost estimates and activity durations. A probability distribution is then calculated from these iteration.What technique is described?
	A、Trend analysts.
	B、Herzberg’s simulation method
	C、Delphi technique
	D、Monte Carle analysis.
	
