試卷名稱(chēng) 2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(3)
考試中心《2017年信息系統(tǒng)項(xiàng)目管理師最新英語(yǔ)模擬題(3)》在線(xiàn)考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

Due to an explosion at the factory of the company’s preferred supplier, the supplier tells informs the project manager that the ordered items for the project cannot be delivered in time, As these items can be easily replaced other items, the project manager uses the second-best supplier as stated within the risk management plan.This is an example of which of the following?
A、a contingency plan
B、a contingency allowance
C、a workaround
D、a fallback plan