The project manager must complete the project in the shortest time possible. To do so, the Project manager decides to schedule non-dependent tasks so they occur simultaneously. Which technique is the manager employing?
	A、Crashing the project timeline
	B、Allowing team members to work overtime
	C、Fast tracking the project
	D、Scheduling a phased implementation
	