The project manager is asked to estimate a project’s costs. The cost and time estimates must be accurate and the detailed cost of every work package is required. Which of the following techniques should be used?
	A、Top-down estimates
	B、Rough order of magnitude estimates
	C、Bottom-up estimates
	D、Parametric estimates
	