A large change order is approved which will impact the project baseline. What should the project manager do once this change is approved?
	A、Re-baseline the project and notify the team
	B、Inform the financial department about the change in budget
	C、Ask for a steering committee meeting
	D、Schedule a project team meeting to discuss options
	