Your project for the U.S. Department of Energy is using earned value analysis as a performance reporting technique. Your project is 201% complete. Results from a recent earned value analysis indicate that the CPI is 0 .67 and the SPI is 0.87. In this situation, you should:
	A、Perform additional resource planning, add resources, and use overtime as needed to accomplish the same amount of budgeted work
	B、Rebaseline the schedule, then use Monte Carlo analysis
	C、Conduct a risk response audit to help control risk
	D、Update to Identify Risks, Perform Qualitative Analysis and Perform Quantitative Analysis
	