The actual expenditure of a project to date is US$850,000, of a US$900,000 total project budget. The current earned value is US$750,000. What is the status of the project?
	A、US$100,000 over budget
	B、US$5,000 under budget
	C、US$100,000 under budget
	D、US$50,000 over budget
	