A project is nearing completion when sponsor A is replaced by sponsor B. What should the project manager do first?
	A、Meet with sponsor B to determine if any project changes are needed.
	B、Finish the project based on the sponsor A's goals.
	C、Begin change control procedures.
	D、Update the stakeholder register.
	
