On some projects, especially ones of smaller scope. activity sequencing. activity resource estimating. Activity duration estimating, and  ( )  are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A. project planning 
B. schedule development
C. cost estimating 
D. time estimating