(  )is a method used in Critical Path Methodology for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities and connects them with arrows that show the logical relationships that exist between them.
A.PERT 
B.AOA 
C.WBS 
D.PDM
 查看答案
                                        查看答案